Friday 23 March 2012

Fifth floor





With the progress of activities, as we reached the fifth floor and we have some photos that show this evolution. As we reported in other posts, the work has been gaining strength and vertical line, because every day has increased the number of employees working on various fronts.
We highlight below some of the services that are running along the floors and are not always possible to be seen live on camera:

 * 1st SS - masonry, and plaster spatterdash; Waterproofing the curtains; beginning of hydraulic (marking drains);

 * 2nd SS - resumption of the execution of drainage;

 * Ground Floor - completion of the capping of the craft, masonry (Block A and B); frame and form preparation for execution of the pillars of the auditorium;

* 1st, 2nd and 3rd floors (Block A and B) start of masonry;

* 4th floor. (Block A and B) completion of the assembly of slabs;

* 5th floor. (Block A and B) shape and frame for subsequent concreting; - External area - start of excavations of the 
Memorial Building.



Monday 19 March 2012

Literacy program

The work of Solomon's Temple also provides to its employees with low education, a better social interaction.
The construction company responsible has created a literacy program, which today is constant in all his works, with a term exceeding one year. As a result, promotes literacy to the maximum possible collaborators. To carry out this project, she has the support and partnership of an NGO (Non Governmental Organisation).
The two hours of classroom occur after normal working hours, from 18:30 to 20:30, Mondays and Thursdays.
The program ensures that employees have all the conditions for attending classes, including infrastructure as: table, chairs, blackboard or white and necessary accessories, notebooks, pens, pencils, rubber, etc ...
One of the intentions of the program is that at the end, they can know to read, write, perform basic math calculations and be aware of general knowledge - which in fact corresponds to the 5th year of elementary school today.
At the end of the program each receive a certificate, but has no official character, just symbolic. However, this knowledge base will serve to continue their studies at accredited institutions to obtain their official certifications.
The goal is to keep the "little school" running and developing its employees by the end of the work.


Sunday 11 March 2012

Use of "cage" for dismantling of shaping forms



The work of Solomon's Temple, by its magnitude, has great challenges in its implementation, one of them is the dismantling of the sliding shaping forms of the pillars. To give an idea, after the workers working in dismantling the shaping forms of the pillars of 30 meters, they were removed from the top by a lifting platform.

 But in the pillars of 50 meters, the platform lift was not enough to remove the workers, requiring intensive work to establish a basic procedure for removal of sliding shaping forms, identifying and mapping the risks inherent in this operation.Was defined then a work plan for implementation
of safety standards and sequence
of activities dismantling .

 The approximate weight of the slide assembly used for molding of these pillars is 2.7 tonnes. The contractor and its partners have developed a "cage" for the enhanced transport of persons, which is suspended by crane, following the decree nÂș 293 de 08.12.2011. It is noteworthy that, because it is a fairly recent legislation is the first time it is applied in a work, showing the line of builders with everything that's new to be used.

Saturday 3 March 2012

Sustainable Practices.




















The Temple of Solomon has the LEED certification as target . Thus, he has worked in the adoption of sustainable practices in an integrated process with the project teams and works.

To do so, count with the collaboration of a group of professionals with the highest competence, such as architects and subject matter experts.

Differentials were incorporated to the design and innovative features that will make the building more efficient and sustainable, in terms of energy, providing users and occupants health and welfare.


Among these Differentials, we can highlight:

>fulfilled with environmental requirements and standards;
>Choose of the area (connectivity with the environment);
>Optimizing the management of construction waste;
>Choose sustainable materials and regional;
>Optimization in the lighting system, air-conditioning and reduction in water consumption;
>Smart elevators, which seek to reduce the waiting time, contributing to the best possible service to users, in addition to reducing energy consumption;
>Building automation;

>The magnitude of the project and respect for the environment of the Temple of Solomonis a milestone in world architecture.