Friday 23 March 2012

Fifth floor





With the progress of activities, as we reached the fifth floor and we have some photos that show this evolution. As we reported in other posts, the work has been gaining strength and vertical line, because every day has increased the number of employees working on various fronts.
We highlight below some of the services that are running along the floors and are not always possible to be seen live on camera:

 * 1st SS - masonry, and plaster spatterdash; Waterproofing the curtains; beginning of hydraulic (marking drains);

 * 2nd SS - resumption of the execution of drainage;

 * Ground Floor - completion of the capping of the craft, masonry (Block A and B); frame and form preparation for execution of the pillars of the auditorium;

* 1st, 2nd and 3rd floors (Block A and B) start of masonry;

* 4th floor. (Block A and B) completion of the assembly of slabs;

* 5th floor. (Block A and B) shape and frame for subsequent concreting; - External area - start of excavations of the 
Memorial Building.



No comments:

Post a Comment