Tuesday 18 June 2013

Huge advances in the area outside

In just one month we had a very significant advance in the services on the facade of the Temple of Solomon, which can be seen around the work.




























Referring to the ventilated facade system, still placing the metal profiles, which are already almost the entire facade, while also advancing the service placing the stones from Israel. We currently have more than 5 square meters (m2) already installed, completely changing the aspect of the work.



As soon as the facade is completely done, we will be placing the stones from Israel in the 32 columns that are surrounding the Temple.


This week We also concluded the coverage of the nave, giving way for numerous other activities that start inside.


No comments:

Post a Comment