But in the pillars of 50 meters, the platform lift was not enough to remove the workers, requiring intensive work to establish a basic procedure for removal of sliding shaping forms, identifying and mapping the risks inherent in this operation.Was defined then a work plan for implementation
of activities dismantling .
The approximate weight of the slide assembly used for molding of these pillars is 2.7 tonnes. The contractor and its partners have developed a "cage" for the enhanced transport of persons, which is suspended by crane, following the decree nÂș 293 de 08.12.2011. It is noteworthy that, because it is a fairly recent legislation is the first time it is applied in a work, showing the line of builders with everything that's new to be used.