Wednesday, 7 November 2012

Several activities of the work





 The work is at an advanced stage with regard to the implementation of its structure, but we still have areas to be concreted, and maintain the same care from the beginning, thus having the same tracking.

However, we, internally, several activities going on at once, among them:

 
 - Masonry (pictured above), which are also well advanced;



- Installations - photos above and below - (electrical; special systems, air conditioning and fire fighting);
- Finishes - pictured below - (ceramic covering) in bathrooms.
 All these services distributed in different floors of the work.

Thursday, 1 November 2012

Activities are being completed


We are facing a work with numerous challenges, as we have talked of more than two years of work. Some activities are being completed. Among them we have the structural and TAG (Tank of Cold Water), which since its design, manufacturing, assembly and now the assembling in the work, we have shown and will continue showing the step by step, logistics and the inherent care in a
system of this complexity.




We informed that the first step – the assembling in the work - has been
completed, but there are still two left: the outer covering of the tanks with
thermal insulation, equipped with a flame retardant additive, and a hydrostatic
test after. 

After being completed these activities will be covered by concrete
structure, being similar to the others, so that will be embedded in the three great
pillars to the right of the front facade (who is at Avenida Celso Garcia looks at the
property). Remembering that now our 
NEW CAMERA LIVE may also accompany all
activities.

Monday, 15 October 2012

The New LIVE Camera

 In the midst of so many activities that happen daily, THE MEMORIAL Building continues being built.

After the conclusion of the foundations, we had
a decrease the rhythm of its activities due to
rainfall.




But at the moment, within the normality, is being carried out part of the superstructure (pillars, beams and slabs).

The slabs and beams are responsible for receiving
the building loads and transmit them to the pillars,
which discharge those loads on the foundations.

 




From now on, all this work and even more will be
demonstrated step by step, since we have a new
camera that allows us to follow this magnificent
building and also the logistics of the work by the
live link: http://www.otemplodesalomao.com/live.html




Saturday, 29 September 2012

Workplace Safety is Priority in the Construction Work






 The Construction took shape and consequently more height. The
highlight for this result is how activities are developed daily. We can
make an analogy to the work as "little ants" (pictured above), so
that each worker develops his part, including continuing the work of another one - a true teamwork.


All this promoted and has been promoting a hard but rewarding
work, focused on employee safety. To get an idea, the contract
between the UCKG and the construction company foresees this
responsibility very clearly. This demonstrates that even before the
beginning of the work we already had a well-developed planning for a construction of this magnitude.


Throughout the construction work, we have been posting
subjects speaking about the safety of the workers, which has
been a priority since the beginning of the activities.
Seeking recognition and reward to the professionals, the
building has a "zero clearance campaign," that by completing a
month without such clearance, there is a reward to the workers.


Thursday, 13 September 2012

The Temple’s Workers





The rain gave us a break in São Paulo, and this dry climate
condition favors even more the various activities that are being
developed in our work site. In this way, we could develop a very
good pace of work, so that we have already reached 36% of the
total project schedule.

An example of this action can be seen on the facade of the
Temple (pictured above), which is almost in its final height of 56
meters.

To achieve all this objective, the construction work has
professionals and consultants who are responsible for all the
monitoring, besides many other contributors that are no less
important, who also assist in this supervision of the work,
reaching already over a thousand, who work in various areas –
 Like in the work site as in the businesses that need to
industrialize or adapt their products for posterior application
on the Temple.


These workers leave their homes very early, to devote
themselves in their own skills.

While others are developing their activities in the evening, so
the builder seeks ways to repay them with something else.

And for everything reported here, when doing monthly
measurements of the work that has being done, we can see the
progress of this great wonder moving forward.


Friday, 31 August 2012

Description of the Activities with the Metallic Structure


This week was lifted the 5th scissors, missing only three to conclude the
coverage of the auditorium. This huge challenge can be demonstrated
in the dimensions of each piece, measuring 81 meters long and 7 meters
high, reaching weigh of 60 tons.
At the end of the scissors assembly, the gap between them will be
completed by specific pieces, which will provide support for the roof tiles
and the bracing pieces, which will be responsible for ensuring the lateral
stability of the scissors.


The thermo-acoustic tiles, an important sealing element, are composed
of steel plates, filled by layers of cement plate, rock wool and other
materials, specified carefully by the acoustic professionals.
Each profiled tile measures 40m long by 40cm wide, which will be joined
by the system of zipping tiles. This system is widely used for construction
of large spans of coverage to ensure perfect sealing of the entire area of
the auditorium (81m x 81m).


Saturday, 25 August 2012

New York Supports The Templo of Solomon (from Bishop Edir Macedo blogue)


 Read this full post in Bishop Edir Macedo Blogue > Click HERE
We’ve watched as people of the UCKG in Brazil, and all over the world, have been helping in the construction of the Temple of Solomon in Sao Paulo. The people here, in Brooklyn, NY, have the same faith and are doing everything they can to help with this glorious project.

One woman mentioned how she had been saving up to visit Brazil in 2014 and watch the World Cup (soccer), but when she heard about the Temple she changed her mind. She is still planning to visit Brazil, but now it will be for the inauguration of the Temple of Solomon. She also made the decision to give and help raise funds for the Temple.

People are believing in this prophecy: “Those who help will become rich,” and many are preparing for a trip to the grand opening.

 
Mrs Greywolf has decided to use her talent as a singer to raise funds for the Temple. She originally came to the UCKG through our TV programs. She was sick, couldn’t go without her asthma medications, could not sleep at night and had serious financial problems, one of which was a court case that had been going on for 10 years. She learned about intelligent faith in the church and was healed. She no longer needs her old asthma medications.

She also won her court case. Her life has been transformed from water to wine. She surrendered to Jesus, was baptized in water and is very happy in her new life.

She came to us with the idea of using her talent to raise funds for the Temple, and so we decided to record this video with her and pastor Albert, the keyboard player of our Brooklyn UCKG. And we are even planning a concert to raise more funds for the Temple of Solomon.

Everyone here has the spirit of helping in the construction, since they know that many souls will be saved, helped and transformed by means of the Temple of Solomon.
Bishop Ubirajara Fonseca
 