Tuesday, 29 May 2012

Memorial building

Preparing the ground

 
During this week, among of the many fronts of work, activities were intensified
where we have the Memorial Building.







The first step was to excavate the site and posteriorly, the foundations have been
performed by the method continuous helix.
We are currently performing the demolition of the stakes to be
made the implementation of the blocks and beams of the foundations.
After this procedure, the sealing of those blocks and beams will be made and
then the release of the forms and the beginning of the superstructure (pillars,
beams and slabs).

Everything we will show step by step during all the construction phases, once the
camera position does not allow us to demonstrate the entire course in the LIVE LINK.

Thursday, 10 May 2012

General Vision of the Work











With the reduction of rainfall, the work has been able to move forward on several fronts.


The activities are distributed throughout the construction site, on all floors, including the Memorial
Building, which after the excavations were carried through the foundations using the method known
as "continuous helix", having stakes of 23 feet deep.


Briefly, we have the following activities:

- At Blocks A and B (6th floor): scaffolding, shaping, framing and concreting of the concrete structure
cast "on site" (slabs, beams and columns), also the installation of protection net surrounding the
building at Block A;

- Installation of preformed parts (slabs) in the construction site;

- Waterproofing of environments in 1st Basement, ground floor (terrace) and curtains;

- Implementation of the rectangular pillars at the sides of the auditorium;

- Marking of points and execution of hydraulic and electrical installations;