Thursday 10 May 2012

General Vision of the Work











With the reduction of rainfall, the work has been able to move forward on several fronts.


The activities are distributed throughout the construction site, on all floors, including the Memorial
Building, which after the excavations were carried through the foundations using the method known
as "continuous helix", having stakes of 23 feet deep.


Briefly, we have the following activities:

- At Blocks A and B (6th floor): scaffolding, shaping, framing and concreting of the concrete structure
cast "on site" (slabs, beams and columns), also the installation of protection net surrounding the
building at Block A;

- Installation of preformed parts (slabs) in the construction site;

- Waterproofing of environments in 1st Basement, ground floor (terrace) and curtains;

- Implementation of the rectangular pillars at the sides of the auditorium;

- Marking of points and execution of hydraulic and electrical installations;