The objective of this blog is to keep you updated of the construction of the Temple of solomon.
Monday, 6 August 2012
Lifting the FIRST SCISSOR metallic.
Since the beginning of May this year we have posted information
about the manufacture and assembly of metal scissors coverage.
We talked about its inspection at the factory, its arrival on the
site, highlighted its special features (more than 80 meters span
and weighs more than 60 000 kilos), showed its assembly in the
construction work since the beginning and the spreading of the work
to night shift, for the installation of this grand structure.
For all this work could be done, there was a thorough commitment
jointly by the contractor, to develop a plan for the assembly and a
validation of the designers of steel structure and of concrete.
The scissor have been lifted over the past week to its final location -
18 meters high, and the method used to lift it was by hydraulic jacks,
with close monitoring.
This is the first of eight metal shears that will be part of the roof of
Solomon's Temple.