- Increase in the number of employees: more than 900 are already allocated in the construction site;
- New equipment and machinery are being made available in the construction work;
- Advance from certain activities according to the original schedule: a good example is the implementation of the metallic structure covering of the auditorium;
- There are activities that their shift are extended by two hours;
- The main action comes to activities with 24-hour shift: cleaning, organization, supply of material in the work fronts, brickwork execution, among others.
No comments:
Post a Comment