Tuesday 21 February 2012

First step complete.


In the last week of 2011, three pillars of 50 meters in height and 7 of 30 meters were completed. 




The work has advanced on several fronts simultaneously, and each day, and this can be verified,  in just seven days completed more seven pillars of the of Solomon's Temple, while facing rainy days.

This time, were raised 4 on the right side and three on the left. This is due to the fact that we have, for this constructive process, uninterrupted 24-hour shifts.


To get an idea in each of these pillars of 30 meters are used approximately 40 cubic meters of concrete, and the higher with 50 meters, around 100 m³.

As we have a total of 32 pillars, 26 to 30 meters and six meters high with 50, will be used in molding its more than 1600 cubic meters of concrete.
In the second week of February was completed the concreting of seven pillars, six of which will be part of the facade of funds and the side. 
With the completion of these, 
now are 24 completed pillars, 
missing five of 30 meters and
three of 50 meters.

These three will be the last, since it requires the completion of installation of the Cold Water Tanks, for its execution.
We know we have many challenges ahead, but the Spirit of Creation is at the forefront of this project.



We would like to thank all employees who have dedicated themselves in this wonderful project and Special all who have contributed financially to effective construction of the temple.